Project Build Phase 1

The FY25 Project Build Phase I projects are listed below with a progress column. PIF is the project initiation form that includes all project specifications, scope, and details. We work with Procurement to ensure these are all inclusive of our specific needs for each project. Once we have these fully developed, the details are included in the RFP that is created for each project.

The first table lists the 27 projects for which we submitted PIFs July 1-7, 2024.

LocationProjectDescriptionTotal CostProgress
Booker T, Washington HSRoofRoof Replacement$6,496,500PIF Under Procurement Review
Booker T, Washington HSWindowsWindow Replacement$5,431,500PIF Under Procurement Review
Cromwell ESHVACReplace Chiller, Boiler, Pumps, RTU, UV, Controls$3,165,000PIF Under Procurement Review
Dunbar ESWindowsWindow Replacement$2,343,000PIF Under Procurement Review
East HSWindowsWindow Replacement$6,390,000PIF Under Procurement Review
Egypt HSHVACReplace Chiller, Boiler, Pumps, RTU, UV, Controls$5,802,500PIF Under Procurement Review
Ford Road ESHVACChiller(2), CT(2), Boiler(2), RTU, Controls$2,110,000PIF Under Procurement Review
Fox Meadows ESRoofRoof Replacement$3,195,000PIF Under Procurement Review
Frayser-Corning ESFoundationRepair NW Exterior Stairwell$315,000PIF Under Procurement Review
Geeter K8RoofRoof Replacement$2,662,500PIF Under Procurement Review
Gordon AlternativeHVACWater cooled chiller, CT, Boiler, Pumps, Controls$1,371,500PIF Under Procurement Review
Grandview MSRoofRoof Replacement$2,236,500PIF Under Procurement Review
Holmes Rd. ESHVACReplace Chiller, Boiler, Cooling Tower and Pumps, Controls$1,688,000PIF Under Procurement Review
Invictus Academy (Airways)WindowsWindow Replacement$5,112,000PIF Under Procurement Review
Kingsbury HSHVACReplace SCUVs, Chiller, AHU, RTU, Controls$5,169,500PIF Under Procurement Review
Norris Achievement AcademyHVACReplace Chiller and Controls$263,750PIF Under Procurement Review
Norris Achievement AcademyWindowsWindow Replacement$1,917,000PIF Under Procurement Review
Oakshire ESHVACChiller(2), Boiler(2), Pumps, UV, Controls$5,802,500PIF Under Procurement Review
Raleigh Egypt MSHVACReplace Chiller, CT, Controls$1,582,500PIF Under Procurement Review
Raleigh Bartlett ESRoofRoof Replacement$1,065,000PIF Under Procurement Review
Rozelle ESFoundationRepair Lower Floor Walls (east end)$157,500PIF Under Procurement Review
Shady Grove PKRoofRoof Replacement$1,065,000PIF Under Procurement Review
Sheffield HSRoofRoof Replacement$6,922,500PIF Under Procurement Review
Sherwood MSFoundationRepair Library Wing Walls$525,000PIF Under Procurement Review
Shrine SchoolHVACReplace Boilers, Pumps, Chillers, Controls$844,000PIF Under Procurement Review
Springdale ESHVACUV, RTU, AHU, Boiler, Pump, Chiller, Controls$8,440,000PIF Under Procurement Review
TLA AdminRoofRoof Replacement$1,597,500PIF Under Procurement Review

 

The second table lists the 25 scopes and PIFs completed July 8-14, 2024.

LocationProjectDescriptionTotal CostProgress
Booker T. Washington HSElectricLED Lighting Upgrade - Gym$35,000Scope development week of July 8
Cordova HSAthleticsOutdoor Lighting (softball, baseball, soccer)$735,000Scope development week of July 8
Cordova HSPavingEntire Lot$1,000,000Scope development week of July 8
Cordova MSPavingEntire Lot$600,000Scope development week of July 8
Craigmont HSElectricLED Lighting Upgrade - Gym$35,000Scope development week of July 8
Craigmont MSElectricLED Lighting Upgrade - Gym$35,000Scope development week of July 8
Crump StadiumAthleticsTrack Resurfacing$600,000Scope development week of July 8
Georgian Hills MSElectricLED Lighting Upgrade - Gym$35,000Scope development week of July 8
Germantown HSFire/Life SafetyReplace Fire Detection System$1,500,000Scope development week of July 8
Hollywood Admin.Fire/Life SafetyReplace Fire Detection System$600,000Scope development week of July 8
Idlewild ESPlumbingReroute Sewer Line to Gym$319,500Scope development week of July 8
Kingsbury MS/HSPlumbingReplace Gas Line$3,500,000Scope development week of July 8
Kingsbury MS/HSAthleticsOutdoor Lighting (softball, baseball, soccer)$300,000Scope development week of July 8
Kirby HSElectricLED Lighting Upgrade - Gym$35,000Scope development week of July 8
Overton HSPavingEntire Lot$600,000Scope development week of July 8
Ridgeway HSElectricLED Lighting Upgrade - Gym$35,000Scope development week of July 8
Ridgeway HSPaving60% of Lot$600,000Scope development week of July 8
Sheffield HSFire/Life SafetyReplace Fire Detection System$700,000Scope development week of July 8
Snowden K8PavingEntire Lot$200,000Scope development week of July 8
Southwind HSElectricLED Lighting Upgrade - Gym$35,000Scope development week of July 8
Southwind HSAthleticsOutdoor Lighting (softball, baseball, soccer)$735,000Scope development week of July 8
White Station HSElectricLED Lighting Upgrade - Gym$35,000Scope development week of July 8
Wooddale HSElectricLED Lighting Upgrade - Gym$35,000Scope development week of July 8